Insight

Construction finance: a developer's guide to non-bank approval timelines

June 19, 2026
Australian residential construction site mid-build with scaffolding in place

Non-bank construction finance approval timelines are driven less by the lender than by the file: how complete the submission is, how quickly the valuation and quantity surveyor reports come back, and how many rounds of questions credit has to ask. A well-prepared file with a clear feasibility and a credible exit can move faster through a non-bank than a bank, but no lender can promise a date, and a thin submission will be slow anywhere.

For a developer, timing is capital. A slow approval can cost a site, a builder's slot in their program or a presale window. Understanding where the time actually goes is the most reliable way to protect it.

Why do developers use non-bank lenders for construction finance?

Mainly for speed and flexibility. Non-bank finance is lending from outside the authorised deposit-taking banks — private credit funds, specialist development lenders and similar. For construction, the advantages are more responsive assessment and loan structures shaped around the project rather than a fixed bank policy: lower presale requirements in some cases, higher leverage where the project supports it, and a willingness to look at mezzanine finance behind the senior loan.

The trade-off is a higher cost of funds, so the numbers still need to work after interest and fees. A non-bank approval that arrives quickly on a project whose margin cannot absorb the pricing does not help anyone.

What drives a non-bank construction finance approval timeline?

Four things do most of the work, and three of them are in the developer's hands.

  • Application quality — complete, accurate, internally consistent documents move fastest. Every gap becomes a question, and every question adds days.
  • Project feasibility — clear costings, a fixed-price or well-supported building contract, presales or lease-up evidence, and a credible exit.
  • Developer experience — a track record of comparable completed projects shortens the conversation; a first project needs more support around it.
  • Lender criteria — each non-bank weighs these differently, has different appetite by location and asset type, and runs its own credit committee. Lender selection matters.

Third-party reports sit across all four. The lender will usually require its own valuation on an as-if-complete basis and an initial report from a quantity surveyor, and neither can start until the valuer and QS have the drawings, building contract, cost plan and program. Our note on the as-if-complete valuation document pack sets out what the valuer will ask for.

What are the stages of a non-bank construction approval?

The sequence is broadly the same across lenders, even if the names differ.

  1. Prepare — assemble the feasibility, cost plan, approvals, building contract, sales evidence and entity documents, and confirm the project is in a lender's range.
  2. Scenario and indicative terms — a short submission to one or more lenders to test appetite, leverage and pricing before full costs are incurred.
  3. Select the lender — weigh terms, certainty and track record, not headline rate alone.
  4. Negotiate terms — rate, leverage, fees, interest treatment, presale conditions and the drawdown regime.
  5. Valuation and QS — reports instructed by the lender from its panel.
  6. Credit approval — formal assessment of the full file, often with conditions.
  7. Documents and conditions precedent — loan and security documents, insurances, builder side deeds and the items the lender needs before the first draw.

A conditional approval is not funding. The period between approval and first drawdown is where many programs slip, because conditions precedent were not identified early enough. Typical examples include the developer's equity being contributed in full, builder's insurances and a side deed, signed presale contracts, and any consents needed from an existing lender on the title.

What causes delays in a non-bank construction approval?

Most delays are predictable, which means most are avoidable.

  • Incomplete applications — a missing cost plan, unsigned building contract or out-of-date financials stalls credit before it starts.
  • Numbers that do not reconcile — a feasibility that disagrees with the QS cost plan, or end values well above what the valuer can support. See what lenders scrutinise in a development feasibility.
  • Last-minute changes — a new builder, a redesign or a change of borrowing entity part-way through resets parts of the assessment.
  • Valuation shortfalls — a lower-than-expected value can force a resize of the facility or more equity.
  • Builder assessment — lenders review the builder's financial capacity and experience, and a builder who is slow to supply information slows the whole file.
  • Late legal issues — easements, planning conditions or title matters that surface only when solicitors review the security.

An illustrative comparison

Illustrative only — not a description of any actual lender's timeframe. Two developers apply to the same non-bank lender for a similar townhouse project. The first sends a complete pack: signed fixed-price contract, QS-reviewed cost plan, current approvals, a feasibility that reconciles to both, and a schedule of presales with deposit evidence. Credit raises a handful of questions in one round, the valuation is instructed the same week, and approval follows the report.

The second sends a feasibility and a draft contract, with the cost plan "to follow". Credit cannot size the facility until the cost plan arrives; when it does, it shows costs higher than the feasibility, so the feasibility is reworked; the valuer then needs revised drawings. The second file goes through three rounds of questions before it reaches committee. Neither lender nor developer was slow — the order of work was.

How can a developer shorten the approval timeline?

By doing the credit assessor's work before the file arrives. In practice:

  • Assemble the core documents first. Our list of the seven documents behind a development finance credit decision is a good starting checklist.
  • Run the feasibility the way a lender will — on conservative values, a realistic program and full finance costs. The development feasibility calculator is a quick first test.
  • Have the QS and the builder engaged and responsive, because the lender's QS will need them.
  • Be transparent about weaknesses. A known issue disclosed up front is a structuring question; the same issue discovered by credit is a trust question.
  • Communicate proactively, and keep one point of contact handling lender questions.
  • Start conditions precedent early — insurances, builder deeds and consents — so approval and first drawdown are not weeks apart.

Understanding how the facility will run after approval also helps. Lenders design the drawdown regime around the QS and progress claims, and a developer who knows how a construction facility is controlled can plan the program around it.

How does Siare help with non-bank construction finance?

Siare arranges senior debt, mezzanine finance and preferred equity, and prepares submissions built for how credit assessors actually read them — which shortens a timeline more reliably than anything else. We match the project to lenders whose appetite fits, so time is not spent on lenders that were never going to approve it, and we manage the questions, reports and conditions through to first drawdown. Our development finance advisory work usually starts before the first lender is approached.

Talk to Siare early — the right structure and a well-prepared submission can make or break your program.

This is general information about business and investment-purpose finance only. It is not financial, legal or tax advice and does not take account of your objectives or circumstances. All finance is subject to lender assessment, valuation and approval, and no timeframe or outcome is guaranteed.

Related reading