
An easement is one of the quietest lines on a title, and one of the most expensive to ignore. It rarely stops a project outright. What it does instead is move the start date, and on a development site funded with debt, a moved start date is a financial event long before it is a construction one. Build-over-easement consent is the approval most often left until the builder is ready to pour, which is exactly the point at which it costs the most.
Most residential and infill development sites in Australia carry at least one registered easement: sewer, drainage, water, power, or a right of carriageway in favour of a neighbour. The easement gives another party a legal right over part of your land, usually to keep infrastructure there and to reach it. Building a structure over or immediately adjacent to that infrastructure requires the consent of the party who benefits from it. That is a separate consent from your planning permit and, in most cases, separate again from your building permit.
The parties involved are rarely just you and the council:
The consent is not a formality. The authority can refuse, or approve subject to conditions that change your footings, your slab level, your setbacks, or your yield.
The sequence that causes the problem is common and entirely logical. A feasibility is run off a title search and a planning overlay. A permit is obtained on architectural drawings that show a building envelope, not a footing detail. Finance is arranged against the permitted scheme. Only when engineering drawings are issued for construction certification does anyone overlay the footing set-out against the easement, and only then does the build-over question become concrete.
An easement may also be shown on title but not accurately located on the ground, so survey and CCTV or potholing work is needed to establish its true depth and alignment. Authorities will generally not assess a build-over application on an assumed alignment. So the discovery of the problem and the start of the evidence-gathering happen at the same moment, at the worst possible point in the program.
Construction facilities are typically drawn progressively against certified works. Before a first construction drawdown, a financier will generally want the building permit, the executed building contract, a quantity surveyor's initial report, and evidence that the project as costed is the project that can lawfully be built. An unresolved build-over-easement application sits directly across that last requirement.
Three consequences can follow, and none of them are neutral:
The builder's exposure is worth stating plainly. A builder who priced a conventional raft slab and cannot start has a program claim, a preliminaries claim, or both. Delay costs do not pause while a consent application is assessed.
The fix is not clever finance. It is ordering the work so the consent question is answered while other approvals are running, rather than after they finish. In practice that means:
That last point matters more than developers expect. A credit team is not primarily reacting to the easement itself. It is reacting to whether the borrower knew about it and had a plan for it.
Our published fire-damaged site at Norlane is the clearest example we have of multiple blockers run in parallel rather than in series. That Geelong site carried a council Emergency Order and a build-over-easement application at the same time, and the two were sequenced together into a funded four-townhouse development rather than being worked through one after the other. The same discipline shows in the Baw Baw Shire RFI at Yarragon, where an arborist, gas abolishment and drainage request was run as a scheduled project with owners and dates, and in the Goulburn Valley Water referral objection at Shepparton, resolved with a single consolidated evidence package rather than an exchange of partial responses. Each is one past matter decided on its own facts, not a benchmark for what another site, authority or lender will do.
Authority approvals behave like a project, not a queue: dependencies, evidence requirements, a critical path. What cannot be scheduled is a consent nobody started.
If an easement has surfaced on a site you are funding or about to fund, talk to us before the drawdown schedule is set, or read how we structure around approval risk in development finance advisory.
This article is general information about business and investment-purpose property finance only. It is not financial, legal, tax, engineering or planning advice, and it does not take account of your objectives or circumstances. Easement, planning and building requirements differ by state, authority and site. Obtain your own legal, planning, engineering and financial advice before acting.