A duplex delivered five months early, then refinanced to hold
Construction facility → residual stock · La Trobe Financial
5 months
ahead of schedule

Hands-on progress-claim management delivered a duplex five months early — with the exit planned in advance, one dwelling sold at auction and one refinanced to hold.
The situation
A two-dwelling duplex development in Altona North, funded by a La Trobe Financial construction facility, running in parallel with several other active projects in the same portfolio.
What we did
We ran the facility hands-on from settlement to completion — managing the full progress-claim cycle, including QS inspection bookings, claim submission, drawdown letters and payment follow-through, so that construction was never waiting on funding. As completion approached we planned the exit before it was needed rather than after: one dwelling to market, one to be retained and refinanced.
The result
The project completed five months ahead of schedule in May 2025. Dwelling B sold at auction on 5 July 2025 for $1,250,000 and settled two months later. Dwelling A was refinanced onto a 12-month La Trobe residual stock loan, letting the client hold the asset without a fire sale and without the construction facility's cost or covenants.
Why it matters
Finishing early only creates value if the finance is ready to flex with you. Planning the exit — sale for one, residual stock for the other — meant an early completion turned into realised profit on one side and a retained asset on the other.
Questions about this case
How early did the Altona North duplex complete?
Five months ahead of schedule, in May 2025.
What happened to the two dwellings?
Dwelling B sold at auction on 5 July 2025 for $1,250,000. Dwelling A was refinanced onto a 12-month La Trobe residual stock loan.
How were progress claims managed?
QS inspection bookings, claim submission, drawdown letters and payment follow-through were managed end to end so construction never waited on funding.
Related reading
This case study is a representative example. Full details and figures are available on request — get in touch to discuss a comparable structure for your project.
{"@context":"https://schema.org","@graph":[{"@type":"Article","@id":"https://www.siare.com.au/case-studies/duplex-early-completion-altona-north#article","headline":"Duplex construction finance, delivered early and refinanced to hold","description":"Hands-on progress-claim management delivered an Altona North duplex five months early, then refinanced one dwelling to residual stock. See the structure.","inLanguage":"en-AU","articleSection":"Case study","about":[{"@type":"Thing","name":"Construction finance"},{"@type":"Thing","name":"Progress claims"},{"@type":"Thing","name":"Quantity surveyor drawdowns"},{"@type":"Thing","name":"Residual stock finance"},{"@type":"Thing","name":"Duplex development"}],"image":["https://cdn.prod.website-files.com/6a2faec687d0075e0137f9ba/6a33c6afcded1e73f47fd4a9_siare-aerial-development.jpg"],"author":{"@id":"https://www.siare.com.au/#organization"},"publisher":{"@type":"Organization","@id":"https://www.siare.com.au/#organization","name":"Siare","url":"https://www.siare.com.au/","logo":{"@type":"ImageObject","url":"https://cdn.prod.website-files.com/6a2faec687d0075e0137f9ba/6a7d2d79d9ee56b9be94a56c_Transparent%20Logo.png"},"address":{"@type":"PostalAddress","streetAddress":"Level 2, 161 Collins Street","addressLocality":"Melbourne","addressRegion":"VIC","postalCode":"3000","addressCountry":"AU"},"email":"info@siare.com.au"},"isPartOf":{"@type":"WebPage","@id":"https://www.siare.com.au/case-studies/duplex-early-completion-altona-north"},"mainEntityOfPage":{"@type":"WebPage","@id":"https://www.siare.com.au/case-studies/duplex-early-completion-altona-north"}},{"@type":"BreadcrumbList","@id":"https://www.siare.com.au/case-studies/duplex-early-completion-altona-north#breadcrumb","itemListElement":[{"@type":"ListItem","position":1,"name":"Home","item":"https://www.siare.com.au/"},{"@type":"ListItem","position":2,"name":"Track Record","item":"https://www.siare.com.au/track-record"},{"@type":"ListItem","position":3,"name":"Duplex construction finance, delivered early and refinanced to hold"}]},{"@type":"FAQPage","@id":"https://www.siare.com.au/case-studies/duplex-early-completion-altona-north#faq","mainEntity":[{"@type":"Question","name":"How early did the Altona North duplex complete?","acceptedAnswer":{"@type":"Answer","text":"Five months ahead of schedule, in May 2025."}},{"@type":"Question","name":"What happened to the two dwellings?","acceptedAnswer":{"@type":"Answer","text":"Dwelling B sold at auction on 5 July 2025 for $1,250,000. Dwelling A was refinanced onto a 12-month La Trobe residual stock loan."}},{"@type":"Question","name":"How were progress claims managed?","acceptedAnswer":{"@type":"Answer","text":"QS inspection bookings, claim submission, drawdown letters and payment follow-through were managed end to end so construction never waited on funding."}}]}]}