Progress claims and QS drawdowns.

The full drawdown cycle — builder's claim, QS inspection, cost to complete, lender release — and the points where it most often stalls.

Construction progress claims

A drawdown is not paid on an invoice. It is paid on evidence.

On a construction facility, money does not move because a builder has issued a claim. It moves because a quantity surveyor confirms value has physically been added to the site, and because the lender's file can answer one question with a number: is there still enough undrawn money to finish this building?

A progress claim is a chain with four links — the builder's claim, the QS inspection, the QS report, the lender's drawdown authority. When one link is incomplete or out of sequence, the money stops. Often nobody has said no; nothing is happening either, while interest runs and the program slips.

What follows is the workflow end to end, what a QS report tells a lender that a builder's claim never does, and where claims stall. General information for developers and builders on business-purpose facilities — your loan agreement, building contract and the QS's scope govern your project.

What the QS report says

Cost to complete is the number that decides the claim.

A builder's claim looks backwards at work done. A lender reads the report forwards, at the money still required.

01

Works in place

The QS values what is physically built and fixed to the site at the inspection date — not what is ordered, delivered to a yard or invoiced. Uninstalled materials are often excluded, so an honest claim can still be certified below the amount claimed.
02

Cost to complete

The figure that governs everything: what remains to be spent to reach practical completion, measured against the undrawn balance. Where undrawn funds fall short of it, the facility is out of balance and the gap usually has to be resolved before more money is released.
03

Variations

Approved variations, provisional sums and prime cost items are reconciled to the original contract sum. Variations agreed verbally on site, or priced after the work was done, are the most common reason a report is qualified — and a qualified report is a slow report.
04

Program and time

The report comments on progress against the program and whether the remainder is deliverable inside the facility term. Delay is a credit issue, not only a builder issue: holding costs, interest and pre-sale settlement dates move with it.
05

Retention

Retention withheld under the building contract sits between developer and builder, but it is a real cost still to be paid — at practical completion and after the defects liability period. It belongs in cost to complete, not discovered at the end.
The workflow

Claim to cleared funds, one sequence at a time.

Most drawdown delays are sequencing failures, not credit failures. Knowing where a claim sits tells you who to chase and what will move it.

01

The builder issues the claim

On the contract's payment terms, against the stage schedule or percentage-complete breakdown, supported by tax invoices, a statutory declaration where required, and written approval for any variation claimed.
02

The claim goes to the quantity surveyor

Through the borrower, broker or lender. QS diaries are the most under-estimated delay on a construction job: booking the inspection when the claim is raised, rather than after the lender asks, saves more time than any other habit.
03

The QS inspects the site

Photographed and measured against the original cost plan line items — which is why a claim mirroring the QS's trade breakdown is assessed faster than one built on the builder's internal accounting.
04

The report issues to the lender

Works in place, cost to complete, variation reconciliation, program commentary and a recommendation on the amount able to be certified. Credit reads the recommendation and the cost to complete together.
05

The drawdown request is lodged

On the lender's own form, signed by the borrower, referencing the QS report and invoices with a clear payment direction. Many lenders also want a fresh statutory declaration, current insurance certificates and evidence the last drawdown was applied.
06

Funds flow

Commonly direct to the builder, or into the nominated funding account against a payment direction. Where the facility requires borrower equity first, that contribution must have been evidenced beforehand, not reconstructed afterwards.
Funding account

What a funding account needs to stay in balance.

"In balance" is the test applied at every claim. Worth running yourself before the QS does.

01
Undrawn facility against cost to complete. Undrawn funds, plus committed and evidenced equity still to come, must cover the QS's figure — not the builder's.
02
Contingency that still exists. A contingency consumed by month four is not a contingency. Lenders read the rate it is drawn as an early warning on the project.
03
Capitalised interest, line fees and holding costs. On many facilities these sit inside the limit and must be funded to completion. A program extension consumes them faster than the cost plan assumed. Their GST and tax treatment is a question for your own adviser.
04
Retention and the final trades. Retention releases, landscaping, driveways, occupancy certificate items and titling costs all fall after the last major stage claim, and are routinely under-provisioned.
Submission checklist

What a claim needs before it leaves your desk.

Requirements vary by lender, facility and building contract. Treat this as a working starting point to check against your own loan documents.

The claim itself
01
Raised on the contract's payment schedule and mapped line by line to the QS cost plan.
02
Tax invoices for the period, reconciled to the amount claimed.
03
Contract sum reconciliation: original sum, plus approved variations, less omissions.
04
Dated site photographs covering the works claimed.
05
Retention deducted in accordance with the building contract.
The supporting file
01
Every variation approved in writing before it is claimed, priced against both contract sum and program.
02
Builder's statutory declaration on subcontractor and supplier payment, where required.
03
Current contract works, public liability and workers compensation certificates.
04
Consultant sign-offs due at this stage — engineer, surveyor, building surveyor.
05
Evidence the previous drawdown was applied, and of any required equity contribution.
Before sending, confirm the undrawn balance still covers cost to complete after this claim is paid. If it does not, raise it yourself with a proposed solution. A lender reacts differently to a shortfall the borrower brought forward than to one it discovers.
Common questions

Where claims stall, and what actually unlocks them.

Why was my claim certified for less than the builder claimed?

Usually because the claim included something outside works in place — materials delivered but not installed, a trade part-completed and claimed in full, an unapproved variation, or a provisional sum claimed at estimate rather than actual. It is rarely an accusation, just a different measurement basis, and the gap closes when the claim is built on the QS's line items.

What does "out of balance" mean, and what happens next?

The QS's cost to complete exceeds the money still available to spend. Responses vary, but commonly involve funding the shortfall before further drawdowns, a reworked cost plan, a facility variation or additional security. What tends to decide the outcome is how early it was identified and how well it was evidenced — discovered at the second-last claim, the options narrow sharply.

What are the most common causes of a stalled drawdown?

Roughly in order: the inspection was never booked; a variation was claimed without written approval; insurances lapsed; the statutory declaration was missing or unsigned; the previous drawdown could not be evidenced as applied; the claim did not reconcile to the cost plan; the lender's form was incomplete or wrongly signed; or the file moved between people and nobody owns it. Very few are credit decisions, and almost all are fixed with a complete package rather than a phone call.

Can a stalled claim be escalated, or do you just wait?

It can be escalated, but only with material. Pressure tends to confirm the lender's caution; a reconciled cost plan, the QS's own numbers, the contractual basis for the request and the consequence of delay give a credit officer something to approve. Outcomes still depend on the lender, the facility and the project — this is not a promise any particular claim can be released.
Proof, not theory

Past files where the claim was the problem.

Historical transactions, shown for process and decision-making — not offers, benchmarks or indications of what any future facility may achieve.

Newport
Cost-to-complete allowance trapped mid-build, the lender's default answer already no. An evidence-based escalation built on the QS's own figures saw $301,364 released within 48 hours on that file.
Read the Newport file →
Altona North
A duplex delivered five months ahead of program through hands-on progress-claim management — claims sequenced, inspections booked early, variations documented as they arose. One dwelling sold at auction, the other refinanced onto a residual stock facility.
Read the Altona North file →
Norlane
A fire-damaged Geelong site carrying a council Emergency Order and a build-over-easement application, sequenced into a funded four-townhouse development. See also the Mosman residual stock file, where a rate was argued down directly with the lender's credit team.
Read the Norlane file →

More completed transactions sit on our track record. The structuring work behind them is covered in development finance advisory, and you can model a project in the development finance calculator.

Stalled claim?

Send the QS report and the claim. We will tell you what is actually blocking it.

Siare has sat on every side of this table — bank credit assessor, private-credit fund manager, property developer and broker. That is why a stalled drawdown gets read as a credit file rather than a complaint. As a La Trobe Financial Preferred Platinum Partner, we also have direct senior BDM and credit access when a file needs a human decision.

Business and investment purpose finance only. Nothing here is an offer of credit, an indication of terms, or a representation that finance, a drawdown or any timeframe can be obtained. All facilities are subject to lender assessment, valuation, quantity surveyor reporting and formal documentation. Case studies describe past transactions and are not a guide to future outcomes. Obtain your own legal, tax and accounting advice.